Flooding concentrated near the stream
The model placed most flooding along the north-western boundary beside the permanent stream. Smaller flows followed existing overland flow paths through the site.
A site-specific assessment to understand flooding, protect flow paths and inform the development of a rural lifestyle subdivision.
Council mapping showed a floodplain affecting the site. The development team needed a more detailed understanding of where flooding would occur and what it meant for the proposed building areas.
Flowpath prepared a site-specific flood risk assessment for a proposed 19-lot lifestyle subdivision at the Riverhead site.
The assessment combined topographical survey, LiDAR terrain information and 2D HEC-RAS modelling to examine the flood extent, depths, water levels and velocities.
The October 2024 report found that none of the proposed building areas were within the modelled floodplain. Smaller overland flow paths still needed to be considered in the layout and future building design.
The model placed most flooding along the north-western boundary beside the permanent stream. Smaller flows followed existing overland flow paths through the site.
The report recommended maintaining the existing flow paths, keeping future buildings clear and considering fencing arrangements where fences cross those routes.
The report recommended avoiding cut and fill within the northern floodplain and specifically assessing any changes to ground levels that could affect floodwater movement.
Use site survey and LiDAR information, with the rainfall, inflow and climate assumptions recorded in the issued report.
Assess the 1% AEP event using HEC-RAS 2D, including flood extent, depths, velocities and water levels.
Identify the implications for proposed building areas, flow paths, fencing, ground levels and floodplain storage.
The report concluded that the proposed development was not expected to worsen flooding on the site or neighbouring properties, provided its recommendations were followed.
That gave the development team a site-specific basis for considering the subdivision layout and the controls needed to retain floodwater movement through the site.
Flowpath's wider civil engineering scope, described in our capability statement, included stormwater, on-site wastewater, potable water, shared rights of way and earthworks. The flood assessment formed part of that coordinated design work.
Case study based on Flowpath's issued Flood Risk Assessment, Revision A, dated 23 October 2024. Findings relate to the development layout and assessment assumptions in that report.
A closer look at the access, drainage and rural setting. Photographs taken in March 2026.
This marketing illustration gives an overview of the lots, access roads and surrounding landscape.
The illustration is reproduced as supplied. Lot labels and sales information belong to the original marketing material.
We prepare flood reports, overland flow path assessments and hydraulic models for property and development projects across New Zealand.
Our current in-house tools help us prepare models, assess results and turn around clear reports efficiently. Send us your site address, proposed work and required timeframe.